22/12/2024
Mining News

Euro Manganese confirms production of 99.9% high purity manganese

Euro Manganese said yesterday that it has produced high-purity electrolytic manganese metal from its demonstration plant at its Chvaletice Project in the Czech Republic.

An external laboratory has confirmed the first HPEMM sent for testing has met the demonstration plant target specifications and was at 99.9% Mn metal purity. High-purity manganese sulphate is now under production in the final module and will be sent for external laboratory testing in due course.

Supported by

The demonstration plant is anticipated to commence acceptance testing in late April. Upon successful completion of acceptance testing, Euro Manganese says it will commence deliveries of Plant HPEMM and/or HPMSM to customers. Customer deliveries of the demonstration plant products is not expected to be required for completion of offtake contracts.

Dr. Matthew James, President & CEO of Euro Manganese, explained further: “Producing high-purity electrolytic manganese metal, HPEMM, from our demonstration plant is a significant milestone and de-risks our process flow sheet. I look forward to receiving confirmation that HPMSM produced is on-spec and completing the commissioning process. We are eager to provide customers with high-purity manganese from our demonstration plant so they can either get started on, or continue with, their qualification process of our products.”

Detail on plant commissioning

Commissioning of the process flowsheet commenced in November 2022 on a module-by-module basis.

The Ore-to-Slurry and Magnetic Separation modules were commissioned prior to the end of 2022 and successfully produced a manganese concentrate from the Chvaletice manganese carbonate tailings. Commissioning of the leaching and purification module commenced in January 2023 and successfully produced a purified solution.

This solution, and both products from the subsequent steps (HPEMM and HPMSM), are required to be sent to an external laboratory that has the specialised measurement equipment required for analysis of the low-level of impurities targeted in the demonstration plant process. External laboratory turnaround times are currently 3-4 weeks, which has caused a slight delay in the commissioning schedule.

Five battery materials stocks we are following in Q2

EC Critical Raw Materials Act is major boost for Euro Manganese

More patents granted for Nano One and its battery materials processes

External laboratory results from the leaching and purification module were received in February 2023, confirming the purified solution met the required specification.

The Electrowinning module successfully produced selenium-free HPEMM flakes in March 2023. This metal was sent to an external laboratory for testing, which has confirmed this metal was produced at 99.9% Mn purity and at the design specification of the demonstration plant.

The final dissolution and crystallisation module has now commenced commissioning and HPMSM will be sent to the external laboratory for testing in due course. The Company will provide an update once on-spec HPMSM is produced.

Representatives from the company which manufactured the Demonstration Plant are expected to arrive on site in late April and the plant will undergo acceptance testing. This will involve running the Plant on a module-by-module basis to confirm each module meets the design specification of product quality, throughput, and reagent consumption.

 

Source: the armchair trader

Related posts

Saudi Arabia expands mining sector to support clean energy transition and global mineral supply chains

David Lazarevic

Exxaro Resources in negotiations to acquire South Africa’s Tshipi Borwa manganese mine

David Lazarevic

Europe’s path to a sustainable EV future: Challenges and solutions for critical raw materials

David Lazarevic
error: Content is protected !!